Test Plan

Revision C

1.

Design tag  : %_design_%

2.1. Data Entry Blog Tag :- %_blog_%

2.4.  Security  development tag :- %_development_%

Each payroll clerk will need a userid and password to login to the system. The system will require the clerks to change the password every 30 days.

  1. Test Strategy Testing Tag :- %_testing_%

The test strategy consists of a series of different tests that will fully exercise the payroll system. The primary purpose of these tests is to uncover the systems limitations and measure its full capabilities. A list of the various planned tests and a brief explanation follows below.

3.1. System Test

The System tests will focus on the behavior of the payroll system. User scenarios will be executed against the system as well as screen mapping and error message testing. Overall, the system tests will test the integrated system and verify that it meets the requirements defined in the requirements document.

3.2. Performance Test %_article_%

Performance test will be conducted to ensure that the payroll system’s response times meet the user expectations and does not exceed the specified performance criteria. During these tests, response times will be measured under heavy stress and/or volume.

3.3. Security Test

Security tests will determine how secure the new payroll system is. The tests will verify that unauthorized user access to confidential data is prevented.

3.4. Automated Test

A suite of automated tests will be developed to test the basic functionality of the payroll system and perform regression testing on areas of the systems that previously had critical/major defects. The tool will also assist us by executing user scenarios thereby emulating several users.

3.5. Stress and Volume Test

We will subject the payroll system to high input conditions and a high volume of data during the peak times. The System will be stress tested using twice (20 users) the number of expected users.

3.6. Recovery Test

Recovery tests will force the system to fail in a various ways and verify the recovery is properly performed. It is vitally important that all payroll data is recovered after a system failure & no corruption of the data occurred.

3.7. Documentation Test

Tests will be conducted to check the accuracy of the user documentation. These tests will ensure that no features are missing, and the contents can be easily understood.

3.8. Beta Test

The Payroll department will beta tests the new payroll system and will report any defects they find. This will subject  the system to tests that could not be performed in our test environment.

3.9. User Acceptance Test

Once the payroll system is ready for implementation, the Payroll department will perform User Acceptance Testing. The purpose of these tests is to confirm that the system is developed according to the specified user requirements and is ready for operational use.

4. Environment Requirements

4.1. Data Entry workstations

  • 20 IBM compatible PCs (10 will be used by the automation tool to emulate payroll clerks).
  • 286 processor (minimum)
  • 4mb RAM
  • 100 mb Hard Drive
  • DOS 3.3 or higher
  • Attached to Banyan Vines network
  • A Network attached printer
  • 20 user ids and passwords (10 will be used by the automation tool to emulate payroll clerks).

4.2 MainFrame

  • Attached to the Banyan Vines network
  • Access to a test database (to store payroll information transferred from LAN payroll system)

5. Test Schedule

6. Control Procedures

6.1 Reviews

The project team will perform reviews for each Phase. (i.e. Requirements Review, Design Review, Code Review, Test Plan Review, Test Case Review and Final Test Summary Review). A meeting notice, with related documents, will be emailed to each participant.

6.2 Bug Review meetings

Regular weekly meeting will be held to discuss reported defects. The development department will provide  status/updates on all defects reported and the test department will provide addition defect information if needed. All member of the project team will participate.

6.3 Change Request

Once testing begins, changes to the payroll system are discouraged. If functional changes are required, these proposed changes will be discussed with the Change Control Board (CCB). The CCB will determine the impact of the change and if/when it should be implemented.

6.4 Defect Reporting

When defects are found, the testers will complete a defect report on the defect tracking system. The defect tracking  Systems is accessible by testers, developers & all members of the project team. When a defect has been fixed or more information is needed, the developer will change the status of the defect to indicate the current state. Once a defect is verified as FIXED by the testers, the testers will close the defect report.

7. Functions To Be Tested

The following is a list of functions that will be tested:

  • Add/update employee information
  • Search / Lookup employee information
  • Escape to return to Main Menu
  • Security features
  • Scaling to 700 employee records
  • Error messages
  • Report Printing
  • Creation of payroll file
  • Transfer of payroll file to the mainframe
  • Screen mappings (GUI flow). Includes default settings
  • FICA Calculation
  • State Tax Calculation
  • Federal Tax Calculation
  • Gross pay Calculation
  • Net pay Calculation
  • Sick Leave Balance Calculation
  • Annual Leave Balance Calculation

A Requirements Validation Matrix will “map” the test cases back to the requirements. See Deliverables.

%_design_%